A power station supplies four regions whose peak loads are 10 000 kW, 5000 kW, 8000 kW and 7000 kW. The diversity factor at the station is 1.5 and the average annual load factor 60 %. Calculate (a) the maximum demand on the station (kW) and (b) the annual energy supplied (kWh).